One more time.....
FOR SAN DIEGO----
Monday and Tuesday are IEEE P1284.4
Wednesday is 1394 Printing
Thursday is IPP
Friday is JMP/PMP/etc
If PMP doesn't need time on Friday then JMP/etc. have more.
Wednesday is already full.
FOR BOSTON---
Monday and Tuesday is 1394 Printing
Wednesday and Thursday are IPP
Friday is PMP/JMP/etc. (maybe only JMP)
(This schedule could be inverted; still trying to clear it up.)
Don
Don
To: nonregistered%internal.notes.ibm.com @ interlock.lexmark.com (pwg) @ SMTP
cc: (bcc: Don Wright)
From: harryl%us.ibm.com @ interlock.lexmark.com (Harry Lewis) @ SMTP
Date: 04/28/97 11:59:30 AM
Subject: PWG> Re: IPP> Re: June Meeting in Boston
Classification:
I don't see where it says the IPP is having 2 days in San Diego.
>IPP continues to maintain the highest priority within the PWG, particularly
>given its short and intensive schedule. If the IPP project needs 2 days in
>June (and I believe it does), then it should be scheduled during the week
>such that other meetings are scheduled around it; this is the approach
>taken for the upcoming meetings in San Diego.
Are they?
I was wondering why they didn't take part of Wednesday when PMP "droped out".
Harry Lewis.